Week in Review: Accomplishments and Progress
2025 Road Program
Surface paving was completed at the Grayslake Feed Store lot, United Protestant Church lot, Center Street, Shorewood Road, Hawley Court, and Atkinson Road. Crews also completed pavement striping at the Feed Store, Church lot, and along Center Street.
North Alley Utility Burial
Crews have installed over half of the planned electrical conduit throughout the North Alley. Four proposed pedestals have also been stubbed in as part of the ongoing electrical service work.
Looking Ahead: Planned Activities
Next week, the contractor anticipates completing the final surface paving on Prairie Trail, Karyn Lane, Silo Hill Drive, Stevens Court, and Kerry Way.
Utility crews are anticipated to continue installing conduit in the North Alley as work progresses from west to east.
Community Impact: What to Expect
As work continues in the North Alley, the Slusser Street exit will be closed periodically, with traffic being redirected to Hawley Street as necessary.
Construction signage has been placed in the downtown area for the 2025 Road Program. As part of the Road Program, Pace Bus Route 570 will be rerouted, see here for more information.
Residents, patrons, and visitors are encouraged to exercise caution and be aware of signage and flaggers identifying changes in vehicle and pedestrian traffic within the project area. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.